


Investing in hydropower means reduced energy bills and long-term sustainability for communities and industries alike.

We are dedicated to pioneering the future of clean energy. As a leader in the hydropower industry, we leverage innovative engineering and sustainable practices to develop and operate projects that provide reliable, renewable power and drive national progress.
Civil Engineer
Installed Capacity
Annual Energy Output
Tons of CO₂ Avoided Annually
Local Jobs Created

The progress in the raised weir area and undersluice is on progress. The project continues to progress steadily across all major components. The elevation gains at the weir, completion of foundational elements at the undersluice, and ongoing earthworks in the pondage area indicate a positive trend toward achieving project milestones.


During the reporting period, notable progress was achieved at the undersluice. Raft concreting has been completed, with rebar works advancing up to 6 meters. Vertical and radial gate embedments are installed, and the left and right walls—measuring 4 meters and 3 meters from the bucket portion—are completed. Backfilling will proceed as the wall height increases, with adjacent rocks being either removed or grouted based on site conditions.


During the reporting period, notable progress was achieved at the undersluice. Raft concreting has been completed, with rebar works advancing up to 6 meters. Vertical and radial gate embedments are installed, and the left and right walls—measuring 4 meters and 3 meters from the bucket portion—are completed. Backfilling will proceed as the wall height increases, with adjacent rocks being either removed or grouted based on site conditions.


In the pondage area, slope cutting and heavy excavation are ongoing along the right bank upstream of the raised weir, spanning approximately 150 meters in length with a slanted height of 27 meters. A structural solution is proposed for this section, involving the construction of an inclined wall with a horizontal beam and boulder packing from an elevation of 2000 meters down to the riverbed. The remaining area is shaped into a gentle slope of 1:3 or 1:4 toward the riverbed.


Headrace pipe (HRP) works are progressing steadily. The alignment is accessible by motorable road, aiding transport and construction. Excavation is ongoing at crossing points, with blasting completed. Pipe laying, concreting of anchor blocks, and support pier works are active along the route. 40 anchor blocks are completed, jacketing is underway, and 4 km of pipe is already laid. Four major crossings for siphons and bridges are under excavation, with designs in progress based on completed topo surveys.

Concreting work up to 6 meters from the crank level (EL.1990.6) has been completed. However, the work is currently on hold, with plans to use pumps from the powerhouse for future concreting activities. The backfilling around the surge tank is already completed. Work Progress: 60% Complete, 40% Remaining.


Excavation from Anchor Block 17 to the concrete casing area upstream of the powerhouse has been completed. A saddle pad is installed in the excavated section to support the penstock pipe. Concrete casing works for the inclined penstock are ongoing upstream of the powerhouse, indicating active construction in that area. Site clearance and preparatory activities for the laying of the penstock pipe are in progress along parts of the penstock alignment. Additionally, bioengineering is proposed for the inclined penstock section to stabilize the soil and prevent erosion.

Civil works at the powerhouse have reached up to the corbel beam level, with rebar installation currently underway. The machine floor slab is partially left open as per the EM contractor’s specifications for embedding turbine and generator components. The turbine casing is expected to arrive soon for later installation. Additionally, the cooling chamber is almost complete, pending only the top slab.

The Isuwa Khola Hydropower Project is a 97.2 MW Peaking Run-of-River scheme designed to deliver 674.30 GWh of clean, renewable energy annually to Nepal's national grid, supporting the nation's sustainable development goals.

We actively engage with and support local communities through various social initiatives, including road construction, gabion works, and assistance for essential services like drinking water and community facilities, ensuring shared growth and prosperity.

The Isuwa Khola Hydropower Project is a 97.2 MW Peaking Run-of-River (PRoR) scheme, set to deliver 674.30 GWh of clean, sustainable energy annually to the national grid.
Our project features state-of-the-art infrastructure including a 6.9 km headrace pipe and a powerhouse with a gross head of 940m, reflecting robust design and construction progress. The overall construction is 65% complete as of June 2025

Beyond power generation, we actively support local communities through initiatives like road construction, gabion works, and essential material assistance for drinking water and community facilities.
Chairman
Director
Chief Executive Officer
Admin & Finance Officer
Civil Engineer
Civil Engineer
Procurement Officer
We are developing a 97.2 MW hydropower project to contribute a significant supply of clean, renewable energy to Nepal's national grid and support national development.

We are developing the Isuwa Khola Hydropower Project, a critical 97.2 MW Peaking Run-of-River scheme in Nepal's Sankhuwasabha District. This project is designed to significantly boost the national energy supply, delivering 674.30 GWh of clean, renewable energy annually. Our comprehensive approach covers every phase, from detailed civil works to advanced hydro-mechanical and electro-mechanical installations, all while fostering strong community partnerships.
Capacity
Annual Generation
Project Cost (Est.) (NPR)
RCOD (Proposed)

Our civil works form the backbone of the Isuwa Khola Hydropower Project, encompassing massive construction efforts across diverse terrains. Key structures like the raised weir, headrace pipe, surge tank, and powerhouse are being meticulously engineered and built to ensure long-term stability and operational efficiency. We prioritize robust construction practices and effective resource management.
Weir & Intake Progress
Headrace Pipe Laid
Powerhouse Progress
Tailrace Progress

The integration of hydro-mechanical and electro-mechanical systems is crucial for energy generation. Our teams are diligently working on the fabrication and installation of critical components such as penstock pipes, radial gates, and turbine accessories. We are committed to deploying cutting-edge technology to ensure the efficient conversion of water power into electricity.
Hydro-Mechanical Progress
Electro-Mechanical Progress
Penstock Pipe Laid (inside casing)
Equipment Delivered:

Power Purchase Agreement (PPA)

Marking a critical step towards project funding.

Chongqing Water and Turbine Work Co. Pvt. Ltd. (CWTW), China.

Original Commercial Operation Date (COD) as per PPA.(2024)

June 2025: Overall construction progress reaches 65%.

February 13, 2027 (Proposed): Revised Commercial Operation Date

The Isuwa Khola Hydropower Project is a 97.2 MW Peaking Run-of-River (PRoR) scheme located in the Makalu Rural Municipality of Sankhuwasabha District, Koshi Zone, Eastern Region of Nepal. It is designed to contribute significantly to Nepal's national electricity network.
The project has an installed capacity of 97.2 MW.
The project aims to supply 674.30 GWh of annual energy to the Nepal electricity network.
As of June 2025, the overall construction progress of the Isuwa Khola Hydropower Project is 65%.
The Proposed Extended Commercial Operation Date (RCOD) for the project is February 13, 2027. The original Commercial Operation Date (COD) as per the Power Purchase Agreement (PPA) was October 13, 2024.
Key civil works include a raised weir (50m x 37m), a side intake with two orifices, a 6911.53m long headrace pipe, a circular surge tank, a 2500m long penstock, and a surface powerhouse (115m x 20m).
The project undertakes various social and community support works, including road excavation (e.g., Thange-Bhanjyang School road), gabion works for protection, financial assistance for community structures (e.g., Yangluwa Gangdhok Gumba), and material assistance for drinking water supply at Jimmy Village.
"The Isuwa Khola Hydropower Project has brought significant improvements to our daily lives, particularly with the road development and access to essential services. It's more than just a power project; it's a partner in our community's growth."

Share holder
"The Isuwa Khola Hydropower Project has brought tangible benefits to our village. The new access roads have significantly improved connectivity, and their support for our local Gumba and drinking water schemes shows a true commitment to community well-being. This project is making a real difference in our lives."

Community Leader, Makalu Rural Municipality
"As a partner involved in the civil works, I've been consistently impressed by the scale and precision of the Isuwa Khola Hydropower Project. The progress on critical structures like the powerhouse and headrace pipe is remarkable, reflecting strong engineering and dedicated execution. It's a privilege to contribute to such a vital national asset."

Construction Manager, Civil Works Contractor
"Our collaboration with K.B.N.R Isuwa Power Limited on the transmission line has been a testament to effective partnership. The project's strategic importance for Nepal's energy future is clear, and we're proud to be part of an initiative that is so crucial for national development and energy independence."

Project Coordinator, Transmission Line Partner

We're here to answer any questions you may have about the Isuwa Khola Hydropower Project. Feel free to reach out through the contact form below or use our direct contact information.
